Report

Estudio Lamela’s proposal is based on complete redevelopment of T1, according to the T2 standard, and completion of the project to build the unfinished area of the piers. The proposal has a period of 17 months for the project and 24 for oversight by the author. The project is to complete the construction of Terminal 2, integrate the architecture and the organization of Terminal 1 with Terminal 2, modernise and enlarge the airport aprons, and carry out a master plan which includes a hotel, office buildings, business centres and car parks.

Technical specifications


Project:
REFURBISHMENT AND EXTENSION T1 TERMINAL WARSAW AIRPORT

Location:
VARSOVIA - POLAND

Client:
PPL

Square metres:
T1 45.000 M2, PPS3 54.000 M2, PIERS T2 24.000 M2

Budget (€):
80 MM

Date project:
2008

End date:
2014